Fruit Storage and chilled packhouse Staffordshire

2020

Every single team member pitched in for this challenging yet fulfilling project. Although complicated and time-consuming, coming up with solutions for a chilled dispatch area and packing room

Project start date was 1 week of April, Lock down meant,

  • Room build started 1st week of June

  •  Refrigeration and Electrical installation 3rd week of June.

  • Dock levelers, doors and shelters, bollards, 1st week of July.

  • Partial commissioning July as customer needed access with incoming crop.

  • 3000 ltr Heat recovery vessel for showers commissioned 

  • Commissioning completed after harvest, with edge protection added 

busby hot water.jpg

Pack house Chiller Worcester

May 2021

This project was to supply refrigeration for an existing customer. 


2254f932-d4ce-4dad-8fa7-9360b68afe16 (1)

120kW Cold Store and Dryng Wall

July 2021

Project DescriptionThis is your Project Description. It’s a great place to describe your Project in more detail. Add images and provide visitors with essential information about your work, including the project length, partnerships or any successful outcomes. To hook new potential clients, show how your work has provided solutions for past clients.

Modern City
Projects: Projects
bottom of page