Our Projects
What We’ve Accomplished
Fruit Storage and chilled packhouse Staffordshire
2020
Every single team member pitched in for this challenging yet fulfilling project. Although complicated and time-consuming, coming up with solutions for a chilled dispatch area and packing room
Project start date was 1 week of April, Lock down meant,
Room build started 1st week of June
Refrigeration and Electrical installation 3rd week of June.
Dock levelers, doors and shelters, bollards, 1st week of July.
Partial commissioning July as customer needed access with incoming crop.
3000 ltr Heat recovery vessel for showers commissioned
Commissioning completed after harvest, with edge protection added
Pack house Chiller Worcester
May 2021
This project was to supply refrigeration for an existing customer.
120kW Cold Store and Dryng Wall
July 2021
Project DescriptionThis is your Project Description. It’s a great place to describe your Project in more detail. Add images and provide visitors with essential information about your work, including the project length, partnerships or any successful outcomes. To hook new potential clients, show how your work has provided solutions for past clients.